Jenny Lind/Rancho Calaveras 4/2007 - Status Report

 

 

A Tank Pump Station

 

Installing a new Ethernet radio

Setting up Communications to F Tank and LaContenta WWTP

 

A to B, A to E

 

Installed soft starts for pumps to reduce water hammer

Installed a new transfer switch for generator.  Added features for over current/voltage

Undercurrent/voltage and spikes

Installed new Motor Control Center

 

Installing a new control panel

 

Pipeline Upgrade

 

August 25, 2006

Hired Design Engineer Consultant to design Jenny Lind Road extension pipeline.  This will complete the loop.

Project designed for 2700 feet of line 12” diameter pipe.

Alternative bid for 7200 feet of line 12” diameter pipe.

 

. Reestablishing B Zone

Constructing PRV on Anderson and Yost

Constructing PRV on Westhill and Garner

 

 

Cal Trans has reviewed plans for permit.  Received Cal Trans encroachment permit. 

Received County encroachment permit.

 

Bid documents prepared. 

Prebid April 20,2007

Bid Date:  May 16, 2007

Award Date:  May 23, 2007

Construction should be completed by summer 2007.

 

602 Tank

 

· Tank under construction

 

· Approximately 2-month construction. Tank completion April 2007

Tank color is Hydro Blue

 

Lettering to say, “Welcome to Valley Springs”

 

·  OES approved 90-day time extension to September 9,2007

 

Calibrating hydraulic model for Jenny Lind

 

· Rebuilt one PRV. Need to rebuild 7 more.

 

· Performed Preventative Maintenance (PM) on PRV’s

 

· Flushing Honda/Myrtle Street area on monthly basis

 

· Began flushing entire Jenny Lind system

 

 

Dennis Court Pump Station

 

· Pipeline work completed

 

Pressure change notification to residents

 

  Control panel submittals reviewed (60 day delivery time)

 

June 19,2007 completion

 

  Building completed

 

  PG & E upgrade released for construction (Single Phase to Three Phase)

 

 

Jenny Lind Water Treatment Plant

 

 

Filter delivered and installed

 

Filter building built

 

Programming already started

 

VFD’s for Raw Water installed

 

Filter startup May 14,2007

 

Solids handling startup August 2007

 

DOHS Permit Amendment complete. Draft under review

 

(document furnished by CCWD 4/07)