Jenny Lind/Rancho Calaveras 1/2007 - Status Report
(
Installed
2 new pumps for backups November, 2006
Purchased
soft starts for pumps to reduce water hammer
Replaced
4-inch section of pipe with 8-inch
Decreased pressure by 5 - 7 psi. Increased gpm by approximately 20
Worked
with PG&E on electrical settings for re-closure
Purchased a new transfer switch for generator. Added
features for over current/voltage
Undercurrent/voltage
and spikes
Installed
sound proofing at station
Hired Design Engineer Consultant to design
Project
designed for 2700 feet of line 12” diameter pipe.
Alternative
bid for 7200 feet of line 12” diameter pipe.
Submitted CEQA document for categorical exemption.
Move
Treosti and Baldwin Pressure Relief Valves (PRV) to Baldwin and McCauley to
take load off B Zone.
Move
Treosti and Usher PRV to
CalTrans
is reviewing for permit. Approximately 3-week review.
Don’t need County encroachment permit. We
are sending them a copy of the plans for review.
Bid
documents being prepared. Waiting for CalTrans approval before finalizing.
Bid
Date:
Award
Date:
Construction
should be completed by summer 2007.
· 602 Tank foundation
constructed
· Site prep completed and tank fabricated
· Construction of new control building starting
· Mobilization/Tank delivery date is
· Approximately 1-month
construction.
· Project completion date is scheduled for
· Working with OES 90-day on time extension in respect
to project closeout and
reimbursement.
· Adjusted 8 PRV’s
· Performed Preventative Maintenance (PM) on PRV’s
·
· Begin flushing entire Jenny Lind system in February,
2007
· Completion date scheduled for