Jenny Lind/Rancho Calaveras 3/2007 - Status Report

 

 

A Tank Pump Station

 

Installing a new Ethernet radio

Setting up Communications to F Tank and LaContenta WWTP

Reviewing quote/ Issuing PO

 

A to B, A to E

 

Purchased soft starts for pumps to reduce water hammer

Received a new transfer switch for generator.  Added features for over current/voltage

Undercurrent/voltage and spikes

Ordered new Motor Control Center

 

Pipeline Upgrade

 

August 25, 2006

Hired Design Engineer Consultant to design Jenny Lind Road extension pipeline.  This will complete the loop.

Project designed for 2700 feet of line 12” diameter pipe.

Alternative bid for 7200 feet of line 12” diameter pipe.

Approved CEQA  categorical exemption.

Move Treosti and Baldwin Pressure Relief Valves (PRV) to Baldwin and McCauley to take load off B Zone.

Move Treosti and Usher PRV to Usher Drive and McCauley to take load off B Zone.

Cal Trans has reviewed plans for permit.  Awaiting Cal Trans encroachment permit. 

Applied for County encroachment permit. Responding to County Comments for permit

Bid documents  prepared.  Waiting for CalTrans approval before finalizing.

Bid Date:  March 15, 2007

Award Date:  April 25, 2007

Construction should be completed by summer 2007.

 

602 Tank

 

· 602 Tank foundation constructed

· Site prep completed and tank fabricated

· Construction of new control building started

· Tank delivered

· Approximately 2-month construction. Tank completion April 2007

· Project completion date is scheduled for 6/11/07.

·  OES approved 90-day time extension to September 9,2007

 

Calibrating hydraulic model for Jenny Lind

 

· Rebuilt one PRV. Need to rebuild 7 more.

 

· Performed Preventative Maintenance (PM) on PRV’s

 

· Flushing Honda/Myrtle Street area on monthly basis

 

· Began flushing entire Jenny Lind system

 

 

Dennis Court Pump Station

 

· Pipeline work almost complete

 

  Control panel submittals reviewed(60 day delivery time)

 

June 19,2007 completion

 

  Building completed

 

  PG & E upgrade released for construction (Single Phase to Three Phase)

 

 

Jenny Lind Water Treatment Plant

 

 

Filter  delivered and installed

 

Filter building built

 

Programming already started

 

VFD’s for Raw Water installed

 

Filter startup May 28,2007

 

Solids handling startup August 2007

 

DOHS Permit Amendment 90% complete

 

 

 

Heney Court/ Dunn Road

 

 

Two new PRV’s constructed and operational