Jenny Lind/Rancho
Calaveras 5/2007 - Status Report
A Tank Pump Station
- Installed a new
Ethernet radio
- Setting up
Communications to F Tank and LaContenta WWTP
A to B, A to E
- Installing a new
control panel
Pipeline Upgrade
- Re-establishing B
Zone
- Constructed PRV on
Anderson and Yost
- Constructed PRV on
Westhill and Garner
- Caltrans has reviewed
plans for permit
- Received Caltrans
encroachment permit
- Received County
encroachment permit
- Awarding Bid
Date: May 23, 2007
- Construction should
be completed by summer 2007.
602 Tank
- Tank constructed
- Painting is scheduled
to start immediately
- Tank color is Hydro
Blue
- Lettering to say,
“Welcome to Valley Springs”
- OES approved 90-day
time extension to September 9, 2007
· Calibrating hydraulic model
for Jenny Lind
- Rebuilt one PRV, need
to rebuild 7 more
- Performed
Preventative Maintenance (PM) on PRV’s
- Flushing Honda/Myrtle
Street area on monthly basis
- Completed flushing
entire Jenny Lind system
Dennis Court Pump Station
- Pressure change
notification to residents
- PG&E (Single
phase to Three Phase) May 31, 2007
Jenny Lind Water Treatment Plant
- Filter installed
- Filter building built
- Programming already
started
- PLC Upgrade started
- Filter startup May
14, 2007
- Solids handling
startup August 2007
- DOHS Permit submitted
Water Conservation
- Signs printed and set
up
- Voluntary
Conservation
Watering Outdoors
- 6:00 PM to 10:00 AM
- Odd
Addresses: Tuesday, Thursday,
Saturday
- Even
Addresses: Monday, Wednesday,
Friday