Jenny Lind/Rancho Calaveras 2/2007 - Status Report
Installing
a new Ethernet radio
Setting
up Communications to F Tank and LaContenta WWTP
Purchased
soft starts for pumps to reduce water hammer
Received a new transfer switch for generator. Added
features for over current/voltage
Undercurrent/voltage
and spikes
Installed
sound proofing at station
Ordered
new
Hired Design Engineer Consultant to design
Project
designed for 2700 feet of line 12” diameter pipe.
Alternative
bid for 7200 feet of line 12” diameter pipe.
Submitted CEQA document for categorical exemption.
Move
Treosti and Baldwin Pressure Relief Valves (PRV) to Baldwin and McCauley to
take load off B Zone.
Move
Treosti and Usher PRV to
Cal
Trans has reviewed plans for permit. Cal Trans is expediting permit
process.
Applied for County encroachment permit. One week turnaround
Bid
documents being prepared. Waiting for CalTrans approval before finalizing.
Bid
Date:
Award
Date:
Construction
should be completed by summer 2007.
· 602 Tank foundation
constructed
· Site prep completed and tank fabricated
· Construction of new control building started
· Mobilization/Tank delivery date is
· Approximately 1-month
construction.
· Project completion date is scheduled for
· OES approved
90-day time extension to
· Rebuilt one PRV. Need to
rebuild 7 more.
· Performed Preventative Maintenance (PM) on PRV’s
·
· Began flushing entire Jenny Lind system
· Pipeline work almost complete
Control panel submittals reviewed(60
day delivery time)
Building completed (Roof to be installed when
panel arrives)
PG & E upgrade released for construction
(Single Phase to Three Phase)
Filter
to be delivered
Programming
already started
Clearwell
tie in completed
VFD’s
for Raw Water ship date
Filter
startup
Solids
handling startup August 2007
DOHS
Permit Amendment to be submitted by end of February 2007
Began
construction of 2 new PRV’s